Auxi Madero Posted July 3 Share Posted July 3 Hello, I would like to know if it is possible to introduce a real event occurring at one PV site into a simulation, which is the ramp-up limitation of the PPC that only allows a setpoint of 20% of the MEC (maximum export capacity). I.e., because of that, the inverters power output does not follow immediately the growths in irradiation at the same speed. Would it be possible to introduce any parameter in the simulation that imitate that behaviour to account that losses? I really appreciate any help you can provide. Best regards. Link to comment Share on other sites More sharing options...
Michele Oliosi Posted July 4 Share Posted July 4 If I understand correctly, when this event happens, there is a more restrictive grid-injection limitation or grid curtailment. There is no functionality to cover that in a single simulation, at the moment. However, you could run two simulations, one with the normal, and the other with the more restrictive grid curtailment limit. If you export the hourly CSV files (https://www.pvsyst.com/help/output_file.htm), you can then use a data analysis or spreadsheet tool to combine the data when you wish during the year. Link to comment Share on other sites More sharing options...
Michele Oliosi Posted July 4 Share Posted July 4 Let us know if I didn't understand the ramp-up part correctly. I am not sure if you are writing about a simple grid curtailment or something more complex. Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now