Hello, i need a help, i have a layout i have made on autocad, converted to a DAE file and it work perfectly.. now i have learned that i can download from pvsyst ground levels, now, how i can adapt my plan layout to the ground level i have downloaded? 

Immagine 2024-12-18 160017.png

Posted

i not know why in that case after i dragger the plant in position on the ground file my modules automatically adjusted based on the ground levels, i had just to lower the ground reticle otherwise pvsyst will give error of conpenetrating objects. now if i want to do that thing again it not work my plant remains flat. help me please

Posted

yes but i still recieve the error of conpenetrating so i have to lower just a little bit the ground . is there a way to also reduce the size of the ground after i have finished to place the layout? and i have another question but of another kind.. if i have a 27 module string, but my pv layout is made of 9 modules arrays , how i can set the string in the shading scenes to make it considere 3 arrays as one string? the minimum x , y values i can set are 1 so i not know if it is possible to do to

Posted

@Alberto Cerrone for an unrelated question, you can check other topics on the forum or create a new topic, please.

There is no need to consider 3 arrays as one string (it is actually not possible, unless you use the detailed calculation model via the “Module layout” option). The partition model is an approximation adapted to regular row arrangements. In such a situation, there is not much difference in having 3 partitions or 1 long partition.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...