CleantechPro Posted September 29, 2022 Share Posted September 29, 2022 Hi, I ran a few simulations for a stand-alone ground-mount solar system with about 6 MW_dc solar/PV DC rating (without any energy storage) with success. Later on, I added a properly sized energy-storage unit (BESS) to capture the excess generation during peak generation instances, and discharge those excess generation (which would otherwise be lost w/o BESS) into the grid during off-peak hours. While the simulation ran with success, EBatDis in the PVsyst report has remained nearly 0 for all months (i.e. the BESS hasn't really been utilized at all). I understand that PVsyst's storage facilities/capabilities are rather limited that but this simple case should have worked with PVsyst. Any help would be appreciated. Thanks. Link to comment Share on other sites More sharing options...
André Mermoud Posted September 30, 2022 Share Posted September 30, 2022 I don't know. To our knowing, the "Peak shaving" feature works quite well. Please send your whole project to support@PVsyst.com, using "Files > Export projects" in the main menu, in order that we can analyse your problem. Link to comment Share on other sites More sharing options...
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now