Hi,

I'm working on a project with a grid limitation of 100 MW at the injection point.

The hourly .csv file shows the E_Grid is actually limited as 99.86 MW.

Any idea why the discrepancy?

The same issue with any other grid limitation values, checking or unchecking the separate loss box.

Also, a similar issue with applying the limitation at the inverter level, except it is seen at EOutInv