Jump to content

Grid limitation discrepancy between setting and hourly CSV?


RoggerJones

Recommended Posts

Hi,

I'm working on a project with a grid limitation of 100 MW at the injection point.

The hourly .csv file shows the E_Grid is actually limited as 99.86 MW.

Any idea why the discrepancy?

The same issue with any other grid limitation values, checking or unchecking the separate loss box.

Also, a similar issue with applying the limitation at the inverter level, except it is seen at EOutInv

Best Regards,appvalley tutuapp tweakbox

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...