TAu Posted June 5, 2019 Posted June 5, 2019 Hello,When I use sub-arrays the economic evaluation tool only takes into account the panels of the first sub-array (100) but takes into account the number of supports for the whole system (810). How can I make it so all the panels and inverters are calculated into the investment?-Tuomas
Hizir Apaydin Posted June 6, 2019 Posted June 6, 2019 Dear Tuomas,Which version of PVsyst are you using ?Could you please export the project you are working on (Menu>File>Export Project) and send it to support@pvsyst.com in order that we can investigate about the issue ?Thank you.
TAu Posted June 10, 2019 Author Posted June 10, 2019 Hi,I'm using PVsyst version V6.78. I'll send the project as you wished.-Tuomas