For even number strings, it's easy enough: Nb. of modules in parallel = 2; Nb. optimizers in series = String length/2
For odd number strings, what would be the best way to model them in PVsyst? (2 modules per optimizer, with the last optimizer having 1 module)
I can't add a subarray with Nb. of modules in parallel = 1, and then add the missing modules, as there must be 14 optimizers in series.
More about the system:
Modules - Hanwha Q.PEAK DUO L-G6.2 430
Optimizers - SolarEdge P860
Inverters - SE33.3K-US
Any tips or tricks that have worked for people in the past?