  1. HELLO. 

    i have a pv project with several iinverters Goodwe GW100K_HT. 

    my problem is : 

    i connect several strings that in total are 13. 

    the inverter has total 10 mppts with 2 dc inputs each( 20 dc inputs in total)

    i have 13 strings to connect. 

    i do this in 5 inverters. 

    in the global system summary i see the number of inverters is 6.6. 

    the correct should be 5. 

    i go to the power sharing and i get the message : the sum of the mppt inputs in the sub-arrays is not a multiple of the number of inverter mppt inputs. 

    the above message is true but it shouldn't be a problem. the inverter allows to connect more strings than the mppts . therefore it is not a problem. 

    how can configure my system so that it is correct ? 

    ( PS. one bypass is to create inverters with the exact mppts for each number of strings that i connect for each inverter.  ( that is not entirely correct because then i will get better (false) yield. but it worked to bypass the problem. in fact this is the only solution that worked. ) 

    i will be waiting for your answer. 
    thank you.  