Grid limitations. Import and export capacity and power factor


Recommended Posts

Posted

Hi,

I have the following limitations from the grid:

Import: capacity: 150 kVA, power factor: 0.95 lag to unity

Export: capacity 15,000 kVA, power factor: 0.98 lead

How should I introduce this in PVSyst? Should be 15 MVA and PF 0.98 lead or 15MVA and PF 0.95 lag?

Thanks.