aortuso Posted April 17 Posted April 17 Good afternoon, I am working for a client on a PV project which is composed by several plot. My client provided one .pvc file per each plot of the project. When I upload the different files, PVsyst automatically places the perimeter in the centre of the coordinates, overlapping it with the previous one. Is it possible to upload all the .pvc files in the same 3D scene, respecting thier relative position? Or is it better to merge all the files and then upload one single (complete) .pvc files? Thanks in advance
Stéphane Posted 6 hours ago Posted 6 hours ago Hi. On the import window of the PVC file, you need to uncheck "Automatic" and to set X, Y and Z to 0: This way each plot will be imported at its original location.
aortuso Posted 4 hours ago Author Posted 4 hours ago Hi Stèphane, thank you for the suggestion. Unfortunately, by setting "Automatic" and to set X, Y and Z to 0, it overlaps in a wrong way the two plots. It seems that PVsyst considers the centre of gravity of the trackers and not the one of the perimeter. I report here below a screenshot of the outcome: the two perimeter should be perfectly overlapped and the structures should be complementary.
Stéphane Posted 3 hours ago Posted 3 hours ago Hi. Thank you for the additional information. PVsyst reads the content of the PVC files and applies a translation if X/Y/Z are not 0. If you don't get the expected results, maybe there is an issue with the PVC files. Can you send us the 2 files by email at support@pvsyst.com? We will check further to identify the source of the issue.
Recommended Posts
Create an account or sign in to comment
You need to be a member in order to leave a comment
Create an account
Sign up for a new account in our community. It's easy!
Register a new accountSign in
Already have an account? Sign in here.
Sign In Now