Aboeyad Posted March 17 Posted March 17 Hi PVsyst team, I would like to ask the possibility to simulate PV project "large-scale 100MWp as an example" + BESS ( AC coupled) in one simulation in PVsyst, is that possible? My concern is that with BESS for AC coupled we will have BESS own Inverters + Inverters for PV as well. Thus, how that can be implemented in PVyst?
André Mermoud Posted March 19 Posted March 19 For the storage in batteries, PVsyst treats the AC production as a whole, without discrimination between inverters. But the problem is probably not here: as I understand you want to shift the PV production to hours where the tariff is more favorable. Sorry, this is not yet implemented in PVsyst. This will be done within some months.