Hi, I want to create a load duration curve with PVSyst. A diagram with the annual hours (h) on the x-axis and the cumulated power (kW/MW) on the y-axis. I couldn't find it anywhere among the predefined graphs in PVsyst, nor could I create it myself with the hourly graphs. I hope anyone had the same problem and solved it! Thank you.

Posted

Sorry, it is not possible to get such a plot directly from PVsyst.

The only way is to create a  CSV hourly file during the simulation, including the variable E_Load (or any other desired energy quantity).

And then you have to elaborate your plot from these hourly values in EXCEL.

 

 