Jump to content

Create load duration curve with PVSyst


Sophie

Recommended Posts

Hi, I want to create a load duration curve with PVSyst. A diagram with the annual hours (h) on the x-axis and the cumulated power (kW/MW) on the y-axis. I couldn't find it anywhere among the predefined graphs in PVsyst, nor could I create it myself with the hourly graphs. I hope anyone had the same problem and solved it! Thank you.

Link to comment
Share on other sites

Sorry, it is not possible to get such a plot directly from PVsyst.

The only way is to create a  CSV hourly file during the simulation, including the variable E_Load (or any other desired energy quantity).

And then you have to elaborate your plot from these hourly values in EXCEL.

 

 

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...