  1. Hi Andre,

    We are Owner's Engineers to a client setting up a 20MW solar PV power plant in India.

    We have always considered the default PVsyst energy report as equivalent to P-50 estimation. We have now been asked to furnish evidence in support. Is there any available literature or description in PVsyst which says the default energy simulation is P-50 value?

    Regards

    Vivek Jayakumar

×
×