Hi,
I have the following limitations from the grid:
Import: capacity: 150 kVA, power factor: 0.95 lag to unity
Export: capacity 15,000 kVA, power factor: 0.98 lead
How should I introduce this in PVSyst? Should be 15 MVA and PF 0.98 lead or 15MVA and PF 0.95 lag?
Thanks.