I have imported a 3D scene (.pvc) carried out with PVCase. The solar field has 372 trackers and the 3D scene imported is been scomposed in 372 objects named ''tracking field #xxx''. I had thought that what I did was all right to launch the calculation of the shading scene with the option linear shadings.

I was a little bit surprised when PVSyst shown me the following alert:
''The backtracking strategy is based on distance and width of trackers. Therefore you should define at least one subfield with several trackers. Please correct the shading scene.''

My question is: why PVSyst ask me to define at least one subfield with several trackers when all these informations are defined in the imported 3D scene of all the PV field (orientation, dimension, pitch, quantity of the trackers).
Based on the above, what is the correct procedure to carrried out the calculation of the linear shadings?

Thanks in advance

Sergio


Top
   
PostPosted: Wed Mar 10, 2021 1:35 am 
User avatar

Joined: Tue Oct 18, 2016 3:31 am
Posts: 358
The trackers imported with PVcase are single, individual tables. PVsyst requires a set of tables to be present in the shade scene. If you select a table in your existing shade scene and open the options, you will see there is one tracker row. If you set the number of trackers to 2, you will be able to utilize backtracking.

Make note that when importing from PVcase, if your trackers are at different slopes in the N-S direction, you may run into errors, especially if trying to model bifacial.


Top
   
PostPosted: Thu May 27, 2021 1:05 pm 

Joined: Tue Jan 19, 2021 9:16 am
Posts: 2
Quote:
I have imported a 3D scene (.pvc) carried out with PVCase. The solar field has 372 trackers and the 3D scene imported is been scomposed in 372 objects named ''tracking field #xxx''. I had thought that what I did was all right to launch the calculation of the shading scene with the option linear shadings.

I was a little bit surprised when PVSyst shown me the following alert:
''The backtracking strategy is based on distance and width of trackers. Therefore you should define at least one subfield with several trackers. Please correct the shading scene.''
iMessage For PC
My question is: why PVSyst ask me to define at least one subfield with several trackers when all these informations are defined in the imported 3D scene of all the PV field (orientation, dimension, pitch, quantity of the trackers).
Based on the above, what is the correct procedure to carrried out the calculation of the linear shadings?

Thanks in advance

Sergio
Backtracking strategy; Comparison of energy gains Using PVSyst component library; Importing component definitions and manual input Building a 3D scene in PVSyst with module layout to view effects of shading and to minimize impact.


Top
   
Display posts from previous:  Sort by  
Post new topic  Reply to topic  [ 3 posts ] 

All times are UTC+02:00


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to:  
Powered by phpBB® Forum Software © phpBB Limited