We need to maintain the plant unavailability in the PVsyst loss diagram between 1.45% and 1.50%, with no flexibility on this requirement. Currently, we are adjusting the date and time to achieve the correct values. Do you have any alternative methods to reach these numbers? The unavailability time fraction and periods are fixed at 1.5% and 1, respectively.image.png.ddd427e68e7c14bb57d43328a4a11a14.png

Posted

Hello,

Unavailability can only be defined as a time fraction, not as a direct production loss. Consequently, the impact on production will be higher if unavailability occurs during peak production hours rather than at night. If your goal is to determine production loss due to system unavailability, you will need to adjust both the time fraction and the specific timing of the unavailability to accurately reflect the desired energy loss.

Posted
On 2/10/2025 at 6:54 PM, Linda Thoren said:

Hello,

Unavailability can only be defined as a time fraction, not as a direct production loss.

Is there a chance you would consider to add an option to add unavailability as direct production loss? A certain %, similar to spoiling losses.

Posted

Hi,

This is not on the road map at the moment. If you wish to have an unavailability in production loss, such as in soiling losses, you can indeed put the unavailability in the soling losses tool instead.  

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...