Hi folks

Regarding to ohmic losses. I have system consists of 120Kwp (PV modules) and 100KW inverter power. The system consists of 18 PV strings , 18 PV modules per string.

I want to connect directly 18 strings on 10 MPPTs/20 Inputs , which means that I don't need combiner box in the system.

Now for ohmic losses , PVsyst define combiner box for the calculations and there is no option to skip it .

My question , how I can calculate the power loss if I have for example 18 PV strings connected directly to the Inverter MPPTs inputs without combiner box in PVsyst ? ?

1.PNG.cfcf271889966116dd1df312a719539c.PNG

Posted
It is showing you the loss there of 0.1%. Set the combiner distance to 0.6m to enable the optimization box to minimize copper mass. it has little effect on the result.

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
×
  • Create New...