alejolop1 Posted April 18, 2020 Posted April 18, 2020 Hi guys, I hope you can help me. I find myself making the estimate of probabilities for a plant, but I must do it year by year for 25 years.my question is: With what values should vary the following uncertainties year by year (during the 25 years)- PV modules model and parameters (the main uncertainty after Meteo)- Inverter efficiency (negligible)- Soiling and module quality loss (highly depending on the site conditions)- Long term degradationthanks!!!!!!
André Mermoud Posted May 24, 2020 Posted May 24, 2020 These are not significant. You can let all these values to 0.See the help "Project design > P50 - P90 evaluations"